Contractor Training • Spring 2026

Deep Lock
Case Studies

Real-world Deep Lock projects broken down step by step — from a $400K stormwater repair to Fire Island vibration isolation. See how contractors turned polyurethane into six-figure paydays.

~59 minutes Spring 2026 Andy Powell, VP of Sales
! ! CASE STUDIES Real Projects • Real Results $ DCP
0
SPP SynchroFlow Project Value
0
Depth of Compromised Soil
0
Pipe Breaches Repaired
0
Vibration Reduction (Fire Island)

Your Guide

Andy Powell

Andy Powell

VP of Sales, Alchatek

In this session, Andy walks through real Deep Lock case studies from the field — projects where contractors turned routine concrete lifting calls into six-figure soil stabilization jobs. You'll see the actual DCP reports, grouting setups, pipe repairs, and post-job core samples that prove the process works.

Andy has personally been in the field on many of these projects, crawling through corrugated pipes, running geoprobes, and developing creative grouting techniques that have become standard practice for Alchatek contractors across the country. This is not theory — it's what happens when you combine Deep Lock training with real opportunity.

Field Grouting Expert
Army Corps Project Experience
$400K+ Single-Project Delivery

What You'll Take Away

4 Things These Case Studies Prove

Every project in this session started small and grew because the contractor knew how to identify the real problem, propose the complete solution, and deliver results that earned referrals.

01

A DCP Changes Everything

The SPP SynchroFlow project went from a simple concrete lifting call to a $400K job because Steve Taylor ran a DCP test and discovered 27 feet of compromised soil. One $350 test paid for itself a thousand times over.

02

Subcontract What You Don't Do

Andy's team hired coring crews, geoprobe operators, and point repair specialists — then handled the grouting themselves. You don't need to do everything; you need to manage the solution and own the customer relationship.

03

Engineer Outreach Creates the Pipeline

Co-branded Lunch and Learns with engineering firms create a two-way referral street. You bring them jobs, they feed you projects — and they'll feed you far more than you bring them. That's how you build a commercial book of business.

04

One Big Job Changes Your Trajectory

Matt and Travis at Lift It Right made more on the SPP project than the rest of their entire year combined. Since then they've done dams, historic buildings, parking garages, and curtain grouting. One win created the momentum for everything after.

Inside the Session

Field Photos & Project Documentation

SPP SynchroFlow case study slide
SPP SynchroFlow Site
Two-component application success stories
Two-Component Success Stories
AP700 pumping setup
AP700 Grouting Setup
DCP test results
DCP Test Results

Session Walkthrough

Inside the Case Studies

Follow along as Andy breaks down real Deep Lock projects from initial discovery through final verification — with field photos, DCP data, and lessons learned at every step.

0:00 – 1:10

Opening & Lift It Right Introduction

Andy introduces Matt and Travis from Lift It Right — a local contractor team he trained nine years ago. Starting from spray foam and rig building backgrounds, they now handle concrete lifting, Deep Lock, seawalls, infrastructure, and crack injection across all three Alchatek divisions.

Loading ramp example Andy Powell presenting Deep Lock how it works
1:42 – 8:00

SPP SynchroFlow: The Discovery

A pump manufacturer needed crane access for a heavy lift, but had 2 inches of settlement near the loading docks. What started as a simple concrete lifting call turned into something much bigger when Steve Taylor ran a DCP and the cone sank 27 feet without a single blow count. A metal plate concealed a 12-foot brick manhole leaking water everywhere.

SPP case study details
Live Andy describes the SPP SynchroFlow discovery
8:00 – 14:00

The Three-Pronged Fix: Pipe Repair, Soil Stabilization, Concrete Lifting

Andy found four breaches in the corrugated pipe where soil was pouring in at 16 feet deep. The team developed a three-pronged approach: point repair the pipe, permeation grout with AP700, and lift the concrete. The proposal grew to nearly $400,000 — from what would have been a routine lifting job.

Pipe breach documentation Andy explaining the approach Two-component success case
14:00 – 21:00

Direct Push Technology & AP700 Grouting

Using a technique Andy learned from "Bob the professional grouter," the team hired geoprobe operators to press holes through the clay, drove oversized 2-inch steel pipes into the 1.75-inch holes, attached ball valves and quick connects, and pumped AP700 at 5% catalyst. The resin traveled through the loose clay, filling voids and pushing out through adjacent holes — proof it was connecting across the entire grid.

Grouting equipment setup
Live AP700 tote hookup with ball valves and wash strainers
21:00 – 31:00

Point Repair & Concrete Lifting

Pelican Underground handled the four point repairs inside the corrugated pipe using fiberglass liner, felt, and epoxy inflated by a bladder — creating structural repairs as strong as the original metal pipe. After the grouting was complete, Matt and Travis lifted the slabs. Post-DCP testing confirmed soil improvement, and core samples showed AP700 had permeated deep into the substrate.

Point repair process Andy teaching in the field Project completion
31:48 – 38:00

Fire Island Vibration Isolation (Frank's Case Study)

Contractor Frank shares how sheet pile driving near Ocean Beach buildings on Fire Island caused catastrophic cracking in CMU foundations. The team built a curtain wall using AP720 and AP600 outside, SWLP-1 underneath, and F400 for waterproofing. Two water bottles demonstrated the result — vibration monitors confirmed 85% reduction. The project won an ASCE award for Building Stabilization.

Fire Island case study video
Live Frank presents the Fire Island vibration isolation project
38:00 – 48:00

Engineer Outreach & Market Expansion

Andy shows how co-branded Lunch and Learn presentations with local engineering firms create a "three-legged stool" — technical supplier, factory-trained contractor, and local engineering group. He walks through the full range of markets unlocked by Deep Lock: agriculture (grain silos in Saskatchewan), Army Corps siphon systems, historic buildings, elevator pits, dam repairs, and solar field stabilization.

Engineer outreach presentation Andy discussing market expansion Market sectors overview
48:00 – 55:00

Residential Opportunities & Shopping Center Projects

Andy shifts to residential work — spotting downspout-driven settlement, checking inside garages for voids with a golf club or golf ball, and always accounting for what's hidden under the garage slab. He covers commercial tripping hazard liability (lawsuits start at $15–20K, can reach $8M) and shows a shopping center project where 12-inch thick slabs were lifted across 110 feet in four hours using jack attacks.

Infrastructure and residential projects
Live Infrastructure projects and commercial tripping hazards
55:00 – 59:00

Wrap-Up & Hands-On Demo Transition

Andy closes with additional case studies — a gravel wall stabilization completed in four hours using exactly the calculated 49.5 gallons of AP720, a 220-foot void fill behind a loading dock, and Army Corps siphon pipe sealing in 105-degree heat at Port Sulphur, Louisiana. The group then transitions to hands-on single component demos with the Poly Shark and grout boxes.

Final case studies Andy wrapping up Single-component applications

Equipment & Applications

From the Field to Your Portfolio

Deep Lock equipment
Deep Lock Equipment
Concrete apron repair
Concrete Apron Repair
NASA Stennis project
NASA Stennis Project
Roadways and bridges
Roadways & Bridges

Full Recording

Watch the Complete Session

Get access to the full 59-minute Deep Lock Case Studies session — including all field photos, DCP reports, grouting techniques, and the Fire Island vibration isolation video that earned an ASCE award. Our team will also reach out to connect you with an Alchatek partner in your area.

Unlock the Recording

Submit the form below to get instant access to the full session recording.

Submit the form above to unlock the full recording.

You're in! The recording is ready below.

Deep Lock Training Series

This is one of seven sessions in the Deep Lock Contractor Training Series. Explore the full program to build your technical skills and sales confidence.

Fill out the form above to access this session's recording. Our team will get you in touch with an Alchatek partner as soon as possible.